King-Mazon Machinery Co., Ltd. Welding Process Instruction

Time:[2015-10-13]

3.3 Drawings, technical documents issued, recycling.

King-Mazon Machinery Co., Ltd. Welding Process Instruction


Welding process instruction is mainly in the following aspects: 1. The contents and scope of the application of the welding technology instruction book: the method of drawing, technical document management organization, management of the contents and requirements, inspection and examination. Is a supplement to the company's quality manual? This standard applies to the company design, technical document management.


2.Welding process instruction book responsibility: design, technical document is one of the company controlled documents; the technical department is responsible for the management of the technical departrtment of the record room responsible for the data archiving, lending, payment and other specific work.


3.The contents and requirements of the management of the welding process instruction


3.1 Design personnel sent disclosure figure into the file, should check pattern of integrity, com-plete, product code, there is no signature of the procedures as prescribed in the (design, audit, and process) and map clarity. The file manager shall give the register of all the drawings to the archives. Return the project supervisor to incomplete drawings.


3.2 Product drawing and design document number method The company's product design and design document numbering method to implement the me-chanical industry standards, namely JB/T5054.4 - 2000 "product design and design document number principle".


3.3.1 Drawings and technical documents are issued by the data storage. 


3.3.2 Departments through the map at the time of collection shall be personally check inventory, think is right after, the signature left check; each department shall not lend each other pattern.


3.3.3 Department, workshop should be assigned concurrently in charge of drafting, and timely and technology ministry archives administrator pattern custody and use, try to plug the loopholes, the technology changes in a timely manner. At the same time, the recycling of waste recycling, the unified treatment of the technical department.


3.3.4 Production patterns happen in the use of fuzzy or damaged and cannot be used, can apply for a replacement to technical department. The technical department in the re issuing of draw-ings, must take back the old chart and record, such as the occurrence of the pattern is lost or have other questions, must be dealt with in time, to explain the reasons for the loss.


3.3.5 Orders at the end of the workshop and staff responsible for drawing pattern returned to the record room. File manager is responsible for verification.


3.3.6 All the drawings and technical documents should be unified registration, classification and storage, so it is convenient to retrieve.


3.3.7 On the drawings, technical data to do security work, strict protection, to prohibit any person to alter. If lost, to find out the reasons for the timely written report technical manager, if ne-cessary, to be held accountable.


3.3.8 To keep the pattern, earnestly fire, anti-theft, anti mildew, moth, check regularly.


3.4 Drawings and technical documents


3.4.1To modify drawings and technical documents, should according to the quality manual "document control procedures, procedures, procedures, by design personnel fill in the notice, the relevant departments countersign and technology change map and timely replacement of each department plans to use.


3.5 Drawings, technical documents of the destruction, the file is invalid or unable to use the file information, and no need to save the information, should fill in the file for the destruction of the application of the technical manager, general manager of the approval of the unified destruction.


3. 6 Drawings and technical folder by the general manager for approval.


4.Inspection and examination of the welding process guide book: check the examination by the technical manager.